Republic of Lebanon

Syr EI-Dania Jbab EI-Homr / EI-Hermel Road Project


 

Loan No.: 356 Interest Rate: 4.5%
Beneficiary: Council for Development and Reconstruction Grace Period: 5 years
Project Cost: KD 7.6 million Maturity: 22 years
Amount of Loan: KD 6.0 million Repayment: 35 semi-annual installments
Date of Loan Agreement: 10/03/1998 First Installment: 5 years following the first disbursement
Date of Effectiveness: -    

 

Objectives: 

The project aims at improving transportation between Al-Bikaa and the country's coastal areas. It also aims at contributing towards the development of those areas.

Description:

The project, which is expected to be completed by mid-2000, consists of two parts: The construction of a 34 km long asphalt road between Syr El-Dania and Jbab El-Homr, and the strengthening of 20 km of the road between Jbab El-Homr and El-Hermel. The project components include:

  1. Civil works: The first part of the project includes the construction of a 7m two-way carriage way with a 1.5m shoulder on each side and all necessary ancillary works, while the second part includes widening and strengthening works and improving all the existing road's related ancillary services.

  2. Consulting Services: These include services required to assist in completing the design, preparing specification and tender documents, and supervising the project implementation.

Financing:

The Arab Fund loan constitutes about 79% of the total project cost. The Lebanese Government will finance the remaining costs, in addition to the land acquisition cost.

 

Back to Main Projects Page

Back to Main Loans Page

 


 

Home | About AFESD | Member States | Board of Directors | Operations | Resources | Loans | Technical Assistance | AFESD Contacts | Tour Headquarters | Special Interest

 

mosaibar4.gif (3740 bytes)

Copyright © 1998 1999 AFESD; All Rights Reserved.